Barclay Mowlem
BHP Riverside Coal Wash Plant
Erect two only 109 sqm/m Delkor Horizontal Belt Filters
United Constructions / MME Joint Venture
BHP Cannington
Fabrication, Erection & Commissioning of one only 64 sqm Lead Horizontal Belt Filter
Fabrication, Erection & Commissioning of one only 38 sqm Lead Horizontal Belt Filter
Transfield
Moranbah North Coal Project
The erection of (3) only 120 sqm Delkor Horizontal Belt Filters ("The Largest Horizontal Belt Filters in Australia")
Simon Carves
Oakey Creek Coal Mine
Fabrication of extensive piping, chutes, tanks and supporting steelwork, Stage 2 Coal Wash Expansion
Queensland Nickel ~ Hatch
Fabrication, Installation and plastic lining of 2 inter-phase chutes - Underneath 1000T ore-bin (Area 310).
Plastic Re-line of 1000T ore-bin (Area 310) - August 1999.
Jaques - (03) 9420 9444
Screening Station 65T, Secondary Crushing Station 27T, Sec Crushing Building 38T, Tertiary Crushing Station 160T, Tertiary Crushing Building 75T, Primary Crushing Station 91T, Product Bins 100T and 180T - August 1998.
Metromix Crushing Plant 150T - October 1998
Metromix Crushing Plant 44T - March/April 1999
KANDOS - Primary Crusher Support Steel
NORMANDY GOLD ~ EXACTOMIX (Northern Territory)
Fabrication & Erection of 2 Jaques Screening Stations, Secondary Crusher Support Steel, 100 Tonne Surge Bin, 2 only Radial Stackers, Fabrication & Erection of adjoining conveyor systems.

SMC United Constructions
Sun Metals Corp Pty Ltd
Townsville Zinc Refinery Plant
Fabrication and weldmaping of Class 1 piping, carbon and stainless steel pipe spools Sulfuric Acid and Gas Cleaning pipelines - November 1999 to March 2000.

ABB Engineers Pty Ltd
Newlands Coal
Fabrication of horizontal belt Filter Building 85T
Fabrication and erection of 2 only 109 sqm horizontal belt filters - March/April 1998
Servicing / Maintenance of Filters - 1999/2001
Mareeba Sugar Mill
Clarifier 6m Diameter - March/April 1998

Q.N.P.L. - Mr. John Owens 0417 633 198
Leaching & Washing Refrigerate Quench Liquor Coolers & Piping Installation - Pipe Rack Relocation (13 pipe runs) - October/November 1999

B.H.P. Saraji Coal Mine
Baker Process - Eimco Belt Filter
Fabrication, Trial Assembly & Installation of (1) only 120sqm Horizontal Belt Filter & adjoining Access Platforms and Walkways - September 1999.

Q.N.P.L. ~ Hatch - Stan Taylor 0408 732 288
Installation of Strategic Feeder (1200 Tonne/Hr Capacity - Samson Feeder) at Solar Ore Reclaim Area.
Fabrication & Installation of impact-table and Skirting. Walk Ways and power-pak platforms. - November/December 1999. ("2 only ~ currently operating in Australia")

Transfield Maintenance ~ Q.N.P.L.
Removal of 8 Tonne Portal Crane above Aerators, Refurbishment and Re-certification of crane structure, Supply and Installation of service platform & ladder, Re-installation of 8 Tonne Portal Crane - August 2000.

Queensland Nickel ~ Water Treatment Facility
O'Donnell Griffen
Erection of Water Treatment Facility Shed approx 16m wide x 80m long x 4m high - July/August 2000.
Supply & installation of various sized Pump Skids; Supply & installation of Stainless Steel Manifolds & Pipework ranging from 150mm Dia to 400mm Dia - September 2000.

Kvaerner Process Systems
Fabrication and Delivery of (1) only 15m long x 2m Dia cooling tower Vessel for Porgera Mine - P.N.G. - February 2001.

B.H.P Cannington ~ Townsville Port
Fabricate, Installation and Protective Internal Lining SC-4 Tripper Conveyor Chute.
Fabrication and installation of New Ship-Loader Carrier Support Columns and adjoining Platforms - March/April 2001.

Queensland Nickel - Chris Fitzgibbons (07) 4772 6200
M.C. Environmental Systems (Sydney)
Refurbishment of (2) only Precipitators at Area 330 - March to June 2001.
Complete Fabrication and Erection of (1) only Precipitator at Area 370 - June to August 2001.

Queensland Nickel ~ Transfield Maintenance
Re-shelling of Roaster #4 during shutdown Area 330; Replacement of 65 tonne Cooler during shutdown Area 330; Concrete repairs to Cooler Tub and Drive Foundations - August/September 2001.